Milestones
-
Notice to Proceed - 04/02/09
-
Install Work Bridge - 07/16/09
-
Start on Fish Ladder Construction - 10/29/09
-
Exit tunnel & pools - 02/15/10
-
Electrical Work - 04/07/09
-
Ladder Testing - 07/15/10
-
Project Completion - 09/01/10